The WVDOH announces its December Specifications Committee meeting, which is scheduled for Wednesday, December 4 at 9:00 a.m. at the WVDOH Building 5 Conference Room 820 at 1900 Kanawha Blvd. E., Charleston WV.  For those unable to attend in person please join via Google Meet, details below.

Critical things to look for in the meeting packet (this is not all encompassing please review the entire packet):

  • Project Specific Special Provision 108 for Project S341-16-16.34 on County Route 16/6.
    • The change removes the drawdown cycle of the No Excuses Incentive Payment and begins disincentive payments of $5,000 immediately if the roadway fails to be returned to service on or prior to day ten following the initial closure.
  • Special Provision (SP) 695 for Mainline Pavement.
    • Revisions remove subsection 695.6-Thickness Testing.
    • This section of the specification has historically been confusing for the Asphalt Alternative, as there was conflicting language wherein Asphalt could be penalized twice through Asphalt specific thickness specifications in section 401(Asphalt Pavements) and 410(PWL) and then again through subsection 695.6-Thickness Testing.
  • Special Provision Subcontractor/Prompt Payment
    • These revisions are due to the implementation of the Civil Rights and Labor module within the AASHTOWare Project (AWP) system. Electronic documentation of subcontractor payments will be required to be completed by contractors and subcontractors in AWP, paper forms/submissions are being eliminated, and oversight of subcontractor payment is being transferred from the Districts to the Civil Rights Compliance Division. Other minor clarifying language changes were also made.
  • Section 601 - Structural Concrete
    • The Revision replaces the Rapid Chloride Permeability test with the Surface Resistivity test and also includes price adjustments based upon the surface resistivity results.

A copy of the agenda and proposals will be posted online at the Specifications Committee Website HERE.  Comments are requested on these Specification changes and Project Specific Special Provisions and may be submitted directly to Janie Adkins, Assistant Specifications Engineer at the WVDOH at janie.m.adkins@wv.gov or DOHSpecifications@wv.gov, or to the CAWV Specifications Committee Chairman, Chad Miller, at cmiller@jfallenco.com, and John Crane at jcrane@asphaltwv.com.  Please share comments in advance of the meeting to ensure they can be reviewed/discussed at the meeting.

TO JOIN VIA GOOGLE MEET

meet.google.com/nsk-yfma-nfh

To join by phone dial +1 475-222-5375  |  PIN: 202072403

Past Posts

MP Committee Meeting – June 25, 2025

By JCrane | 2025/06/11

The WVDOH announced their upcoming Materials Procedures (MP) Committee meeting which will be held in person on June 25 at 10:00 a.m. at the Materials…

WVDOH STIP Amendment 4 – Comment Period Open

By JCrane | 2025/06/11

The WVDOT is seeking input on their latest revision to their Statewide Transportation Improvement Program (STIP).  The STIP is a financially constrained document that is…

WVDOH Releases Surplus Funding Projects

By JCrane | 2025/06/11

Tuesday, June 11th, 2025, the WVDOH released a list of projects that will be funded from the transfer of general revenue surplus funds.  The complete…

WVDOH June Material Indices

By JCrane | 2025/06/02

WVDOH has released the Asphalt, Concrete and Fuel price adjustment indices for the month of June 2025 as shown below.

Period – 6/1/2024
#2 Fuel (Gal) – $2.2483
Asphalt (Ton) – $579.00
Cement (Ton) – $282.40

Historical and individualized information can be found on our Index page.

WVDOH Standards & Manuals Committee-June 4

By JCrane | 2025/05/28

The WVDOH Standards & Manuals Committee’s next meeting will be held in person on April 2, 2025, at 9:00a.m. in Room 820 in Building 5…

WVDOH May Material Indices

By JCrane | 2025/05/02

WVDOH has released the Asphalt, Concrete and Fuel price adjustment indices for the month of May 2025 as shown below.

Period – 5/1/2024
#2 Fuel (Gal) – $2.2493
Asphalt (Ton) – $579.00
Cement (Ton) – $289.40

Historical and individualized information can be found on our Index page.

WVDOH Specification Committee – May 7, 2025

By JCrane | 2025/04/24

The WVDOH announces its May Specifications Committee meeting, which is scheduled for Wednesday, May 7 at 9:00 a.m. at the WVDOH Building 5 Conference Room…

Gov. Morrisey Signs Amended Budget Bill

By JCrane | 2025/04/21

On Thursday evening April 17, following the vetoing of several line items, Gov. Patrick Morrisey signed into law a version of House Bill 2026, the…

WVDOH Sweeps 2024 Perpetual Pavement Awards

By JCrane | 2025/04/17

The WVDOH was among 15 other Agencies across the country to earn honors for long-life asphalt pavements which deliver sustainable performance.  Awarded annually by the…

National Work Zone Awareness Week 2025

By JCrane | 2025/04/15

Work Zone Awareness Week (WZAW) has been successful in spreading awareness for work zone safety across the country because of participation from organizations and individuals…